Contract · Letter C

Concurrent Delay

Two or more delay events, one owner-caused and one contractor-caused, running in the same window and each independently capable of delaying completion.

By Dr. Hassan Eliwa, PhD · Founder of PMMilestone.org and PMMilestone.com · Updated 2026-07-02

Definition

Concurrent delay arises when two or more delay events overlap in time and each, on its own, would have delayed the project's completion date. Typically one event is an employer risk (owner-caused or neutral, such as a late design release or exceptional weather) and the other is a contractor risk (contractor-caused, such as slow procurement or resource shortages). The legal and commercial question is: who pays for what? Concurrent delay is one of the most litigated topics in construction contracts and one of the least well understood on site — most disputes I have seen involve at least one party quietly hoping the other has not spotted the concurrency.

Why It Matters

The answer determines whether the contractor gets time (EOT) only, time and money (EOT + prolongation), money only, or nothing. Different jurisdictions and contract forms answer this differently. English law under the SCL Delay and Disruption Protocol (2nd ed.) generally allows an EOT for concurrent delay but disallows prolongation costs for the concurrent period. US federal contracts have historically used "apportionment" where feasible. FIDIC contracts as of the 2017 suite explicitly cross-reference the SCL approach in guidance. Getting this wrong on a live claim can be a seven-figure error.

Real-World Construction Example

On a 42-storey commercial tower, the owner released the podium façade design six weeks late. In the same window, the contractor's precast subcontractor entered administration, halting panel supply for eight weeks. The critical path ran through the façade. The contractor claimed a full eight-week EOT with prolongation of $1.8m. Analysis under a time-impact approach showed six weeks were genuinely concurrent — both events would independently have delayed completion by six weeks — and two weeks were contractor-only. The final award: eight weeks EOT (the contractor is not penalised on time), but prolongation costs paid for only the two weeks of contractor-only delay. The owner accepted the analysis because the schedule quality was strong: baseline logic was defensible and the contemporaneous updates showed the concurrency clearly.

Real-World IT / Agile Example

Concurrent-delay reasoning applies to fixed-price software programmes with hard external dates. A regulatory reporting platform had a mandated go-live. Two things slipped in the same eight-week window: the client's data-migration source (a legacy mainframe extract) arrived seven weeks late, and the vendor's identity provider integration was five weeks behind due to internal staffing gaps. In the eventual commercial settlement, the parties agreed the delay was concurrent for five weeks and client-only for two. The vendor absorbed its own costs for the five concurrent weeks; the client covered extension costs for the two client-only weeks. The lesson translates cleanly from construction: without contemporaneous evidence of which team was blocking which, the concurrency argument evaporates.

Analytical Methods

  • Time impact analysis — insert each delay event into the schedule at the point in time it occurred, and observe its independent impact on completion.
  • As-planned vs as-built windows — compare planned progress to actual progress in short windows (typically monthly) and attribute delay in each window.
  • Collapsed as-built — remove each delay event from the as-built schedule to see how completion would have shifted without it.

Expert Tips

  • Document contemporaneously. The single biggest driver of concurrent-delay outcomes is the quality of the monthly progress records. Retrospective reconstruction is always inferior.
  • Update the schedule monthly with genuine as-built dates. A schedule that only shows "planned" progress is useless for concurrency analysis.
  • Separate float ownership. Contracts that say who owns float remove one entire argument.
  • Do not conflate "concurrent" with "sequential". Two delays back-to-back are not concurrent; only overlapping ones are.
  • Get delay analysts involved early. A £5,000 early advisory review often prevents a £500,000 late dispute.

Common Mistakes

  • Claiming full prolongation costs for concurrent periods (rarely succeeds).
  • Ignoring contractor-caused delay when arguing an EOT — courts and adjudicators are unimpressed.
  • No contemporaneous schedule updates, so concurrency cannot be proved either way.
  • Confusing concurrency with cumulative delay from many small unrelated events.
  • Applying US "apportionment" logic under an English-law contract (or vice versa) — the analytical rules differ.

Practical Lessons Learned

  • The party with the better schedule almost always wins the concurrency argument, regardless of the underlying facts.
  • Standing joint sit-downs between the owner's PM and the contractor's planner every month — reviewing progress line by line — dramatically reduce eventual dispute cost.
  • When both sides agree in real time that a period was concurrent, settlement is fast; when one side pretends concurrency did not exist, disputes drag out for years.

Key Takeaways

  • Concurrent delay = overlapping owner-risk and contractor-risk events, each independently critical.
  • Under SCL and most modern contract forms: EOT is granted, prolongation costs are not, for the concurrent period.
  • Contemporaneous schedule updates decide most concurrency arguments.
  • Different jurisdictions apply different tests — check your contract's governing law.

Related Encyclopedia Entries

Related Research Articles, Case Studies & Tools

Frequently Asked Questions

  • Does concurrent delay always mean the contractor gets an EOT but no money?
    Under English law and the SCL Protocol, generally yes for the concurrent period — EOT protects the contractor from LDs, but prolongation is only paid for owner-only delay. US federal contracts sometimes apportion costs. Always check your governing law and contract wording first.
  • How do I prove concurrency?
    With contemporaneous schedule updates, dated correspondence, and site diaries that show both delay events were active in the same window and each was independently on the critical path. Retrospective reconstruction from memory rarely succeeds.
  • Is a two-day owner delay 'concurrent' with a six-week contractor delay?
    Only for the two days of overlap. Concurrency is a window analysis, not a whole-project label. Most real cases involve partial concurrency, not full concurrency across the whole delay.
  • What if my contract is silent on concurrency?
    You fall back to the governing law's default position. English law leans toward the SCL Protocol; US federal contracts lean toward apportionment; civil-law jurisdictions vary. Never assume — check with counsel before submitting a claim.
  • Do delay damages liquidated damages apply during concurrent delay?
    If the contractor is granted an EOT covering the concurrent period, LDs do not apply for that period. That is the practical value of the EOT to the contractor — LD protection, without the prolongation payment.
  • Can I claim disruption costs separately from prolongation?
    Sometimes. Disruption (loss of productivity) is a distinct head of claim from prolongation (time-related site costs) and may survive concurrency arguments if the disruption is genuinely owner-caused. This is technical territory — get expert advice.
  • Does agile software have concurrent delay?
    Fixed-price agile programmes with hard external dates absolutely do. The concept and the evidence needed (contemporaneous logs of who blocked what and when) translate directly. Time-and-materials agile contracts do not usually generate the same dispute because the client is paying by the sprint anyway.
  • Which calculators on PMMilestone.org apply to Concurrent Delay?
    For Concurrent Delay, the most relevant tools on the flagship platform are the EVM, SPI and CPI calculators on PMMilestone.org. They reproduce the formulas referenced in this entry against your own project data.
  • What is a common misconception about Concurrent Delay?
    That the topic is well-defined across all references. In practice, definitions vary between PMBOK, PRINCE2, AACE and ISO 21500 — this entry uses the definition most aligned with field practice on capital projects, and flags where the standards diverge.
  • Which related encyclopedia entries should I read alongside Concurrent Delay?
    Read Earned Value Management, Critical Path Method and the DCMA 14-point assessment next. The full A–Z is available in the PMMilestone Encyclopedia, and quick one-line definitions live in the PM Glossary on the flagship platform.
  • How does Dr. Hassan Eliwa's research treat Concurrent Delay?
    Dr. Hassan Eliwa's research focuses on owner-side project controls, schedule integrity and forensic delay analysis on capital construction and power programmes. Concurrent Delay is treated through that lens — what a planning or controls engineer is expected to do with it on a live project, not its textbook definition alone. See the full research library at PMMilestone Research Articles.
  • How is Concurrent Delay defined on PMMilestone Research & Insights?
    Two or more delay events, one owner-caused and one contractor-caused, running in the same window and each independently capable of delaying completion. For the full treatment, see the definition, principles, applications and related entries above — every encyclopedia entry follows the same research-grade structure.

People also ask

Follow-up questions practitioners search for next — each one points to the calculator, template or reference entry that answers it.

Related Entries

Browse more in this category

More in Contract

View all Contract entries →

Further reading on PMMilestone.org

Curated companion resources hosted on the flagship platform, PMMilestone.org.

Related Encyclopedia Entries
Career Guides
Tools on PMMilestone.org
Buy me a coffee