Fragnet (Fragmentary Network)
A small, self-contained network of activities inserted into a baseline schedule to model a delay, change, or recovery scenario without disturbing the main logic.
Definition
A fragnet, short for fragmentary network, is a small, self-contained set of activities and logic links that plugs into a larger CPM schedule to represent a specific event — most often a delay, a change order, an acceleration, or a proposed recovery plan. The fragnet is developed separately, reviewed for internal correctness, and then integrated into the baseline (or into a copy of the current update) to measure its schedule impact. Fragnets are the working currency of forensic scheduling and Time Impact Analysis.
Origins
The term entered mainstream scheduling practice through the U.S. Army Corps of Engineers modification impact evaluation guidance in the 1970s and was later codified in AACE International Recommended Practice 52R-06 and the Society of Construction Law Delay and Disruption Protocol. Every serious delay-claim methodology in use today — Time Impact Analysis, Windows Analysis, and Collapsed As-Built — relies on properly built fragnets.
Anatomy of a Fragnet
- Inserted activities — new work required by the change or delay event.
- Logic ties into the host schedule — clear predecessor and successor links to existing activities.
- Duration justification — every duration has a source (crew and productivity, subcontractor confirmation, supplier lead time, or historical benchmark).
- Calendar assignment — the fragnet must respect the calendars in force on the affected activities (weather, shutdowns, holidays).
- Reference documents — RFIs, change directives, correspondence, and photographs that support the inserted logic.
Real-World Construction Example
On a 22-storey commercial tower, the owner issued a directive to change the curtain-wall system from unitised to stick-built on floors 8 through 22, four months into construction. The scheduler built a 47-activity fragnet covering re-engineering, sample fabrication, procurement of new extrusions (a 14-week lead item), mock-up, and installation crew re-training. The fragnet was inserted into a copy of the current update, and the critical path shifted by 63 working days. The contractor issued a change order supported by the fragnet; the owner and their independent scheduler negotiated the delay to 58 days after adjusting two of the durations. The claim closed in eight weeks — fast, by industry standards, because the fragnet made the argument transparent.
Real-World IT / Agile Example
Fragnets are less common in pure agile work but appear routinely on delivery programmes with hard dependencies — for example, migrations to a new payments processor. A telco delivery programme discovered mid-flight that a regulatory change added a new compliance certification, needing a specialist third-party lab. The programme scheduler modelled a 21-activity fragnet — vendor selection, contracting, sample submission, remediation cycles, certification, and rollout — and inserted it into the master delivery plan. The fragnet showed a 47-day slip to the mandatory go-live. Rather than argue in prose, the team walked stakeholders through the fragnet at the steering committee, secured the descoping decisions needed, and preserved the regulatory date.
Best Practices
- Build the fragnet in isolation first, then integrate. Building directly into the master is where errors originate.
- Every duration and every logic tie must be traceable to a document.
- Assign the correct calendar; a fragnet built on the wrong calendar produces the wrong answer.
- Preserve a clean baseline copy for the "before" comparison — you will need it in any dispute.
- Keep the fragnet contained to the affected work; global logic rewrites disguised as fragnets are a red flag in claims review.
Common Mistakes
- Inserting a fragnet without corresponding removal or suspension of superseded activities.
- Overreaching — including work that was already delayed for other reasons.
- Missing logic ties on both sides; a fragnet with predecessors but no successors floats freely and doesn't drive dates.
- Using the current update instead of a defensible reference schedule.
- Failing to document the sources; the fragnet is only as strong as its evidence.
Expert Tips
- Draw it on paper first. A fragnet with more than 20 activities is easier to sketch than to model. Sketch, review, then build.
- Keep two versions: the pure fragnet (unimpacted) and the integrated schedule (impacted). Reviewers will ask for both.
- Colour-code inserted activities in the integrated version. Reviewers appreciate visual clarity.
- Peer-review before submission. Have a scheduler with no stake in the outcome walk the logic. Nine times out of ten they find at least one flaw.
- Never insert a fragnet into a schedule that has been retroactively "cleaned up". The claim will be denied on integrity grounds alone.
Practical Lessons Learned
- Fragnets settle disputes faster than narrative arguments — a well-built fragnet turns a claim negotiation into an engineering conversation.
- The claims that fail are almost always the ones with sloppy logic or missing documentation, not the ones with weak underlying merit.
- Owners' schedulers respect a fragnet that shows its work. Hiding assumptions guarantees pushback.
Key Takeaways
- A fragnet is a small, focused subnetwork used to model a delay, change, or recovery.
- Every duration and link must be evidence-backed and calendar-correct.
- Build in isolation, then integrate into a defensible reference schedule.
- Fragnets are central to Time Impact Analysis, Windows Analysis, and modern delay claims.
- Transparent, well-documented fragnets close claims faster and cheaper than prose arguments.
Related Encyclopedia Entries
- Time Impact Analysis
- Critical Path Method
- Change Order Management
- Extension of Time
- As-Built Schedule
Related Research Articles, Case Studies & Tools
Frequently Asked Questions
How large should a fragnet be?
Large enough to model the change honestly and no larger. Most fragnets are 10 to 60 activities. If yours crosses 100 activities you are probably rewriting a portion of the master schedule rather than modelling a discrete event.Do I insert a fragnet into the baseline or the current update?
Depends on the analysis method. Time Impact Analysis (a prospective method) inserts into the update that reflects status just before the delay event. Retrospective methods use a defensible reference schedule contemporaneous with the event. Never insert into a schedule that has been retroactively edited.Can a fragnet reduce durations rather than add them?
Yes — acceleration and recovery fragnets do exactly that, showing how proposed measures (crew increases, overtime, resequencing) shorten the projected finish. The same integrity rules apply; every reduced duration needs justification.Do owners accept contractor-built fragnets?
Owners accept fragnets that show their work — logic ties, duration sources, and supporting documents. They reject fragnets that look like backward-engineered claim padding. Transparency and peer review are the difference between acceptance and pushback.What software do people use to build fragnets?
The same CPM tools used for the master schedule — Primavera P6, Microsoft Project, Asta Powerproject, Deltek Acumen Fuse for review. The tool matters less than the underlying discipline; a rigorous fragnet in MS Project is stronger than a sloppy one in P6.Are fragnets used in agile programmes?
Occasionally on delivery programmes with hard dependencies and regulatory deadlines. Pure product-mode agile teams do not typically use them because their planning is iterative rather than network-based. Programme-level fragnets can be very useful for cross-team dependency modelling.What's the single biggest reason fragnets are rejected?
Undocumented durations. A reviewer who cannot see where a 15-day duration came from cannot defend accepting it, so they push back. Cite every duration to a source — a subcontractor letter, a productivity study, a supplier confirmation — and rejection rates drop dramatically.Which calculators on PMMilestone.org apply to Fragnet (Fragmentary Network)?
What is a common misconception about Fragnet (Fragmentary Network)?
That the topic is well-defined across all references. In practice, definitions vary between PMBOK, PRINCE2, AACE and ISO 21500 — this entry uses the definition most aligned with field practice on capital projects, and flags where the standards diverge.Which related encyclopedia entries should I read alongside Fragnet (Fragmentary Network)?
Read Earned Value Management, Critical Path Method and the DCMA 14-point assessment next. The full A–Z is available in the PMMilestone Encyclopedia, and quick one-line definitions live in the PM Glossary on the flagship platform.How does Dr. Hassan Eliwa's research treat Fragnet (Fragmentary Network)?
Dr. Hassan Eliwa's research focuses on owner-side project controls, schedule integrity and forensic delay analysis on capital construction and power programmes. Fragnet (Fragmentary Network) is treated through that lens — what a planning or controls engineer is expected to do with it on a live project, not its textbook definition alone. See the full research library at PMMilestone Research Articles.How is Fragnet (Fragmentary Network) defined on PMMilestone Research & Insights?
A small, self-contained network of activities inserted into a baseline schedule to model a delay, change, or recovery scenario without disturbing the main logic. For the full treatment, see the definition, principles, applications and related entries above — every encyclopedia entry follows the same research-grade structure.
People also ask
Follow-up questions practitioners search for next — each one points to the calculator, template or reference entry that answers it.
Where is this in the glossary?
Quick-lookup definitions across 1,200+ PM terms. PM Glossary on PMMilestone.org ↗
Which learning track covers this end-to-end?
Structured tracks from beginner planner to programme controls director. Project Controls Academy ↗
Which book goes deeper than this entry?
Practitioner field handbooks with worked numerical examples. Books & Publications ↗
Which calculator on PMMilestone.org applies here?
The integrated EVM workbook covers most cost-schedule diagnostics. EVM Calculator ↗
Related Entries
More in Schedule
- Letter AActivity Definition
The process of identifying and documenting the specific actions required to produce project deliverables, decomposing work packages into discrete schedulable activities.
- Letter BBaseline Schedule
The approved, time-phased plan against which actual progress is measured and variance is reported throughout the project.
- Letter CCritical Path Method (CPM)
A deterministic scheduling technique that identifies the longest chain of dependent activities and the activities that drive the project completion date.
- Letter DDependency Mapping
The systematic identification of internal, external, mandatory, and discretionary relationships between activities so the schedule logic mirrors the way work really has to happen.
- Letter EEarned Schedule
A time-based extension of earned value that converts schedule performance into units of time, fixing EVM's well-known late-project blind spot.
- Letter FFloat Management
The deliberate planning and consumption of schedule float (slack) to absorb uncertainty and prioritise management attention.
Further reading on PMMilestone.org
Curated companion resources hosted on the flagship platform, PMMilestone.org.
- For practitioners who want to go deeper, the Learning Tracks.
- Engineers researching this topic typically continue with the Books & Publications.
- A practical companion to this entry is the EVM Calculator.
- Closely related on the flagship platform is the Schedule Health Checker.
- Useful alongside this article is the PMMilestone.org knowledge hub.