Material Submittal Approval
The formal loop through which proposed products are reviewed against the specification and approved before procurement — the quiet path that decides whether long-lead items arrive on time or six weeks late.
Definition
Material submittal approval is the contractual process by which a contractor proposes the actual products, systems and finishes it intends to install, and the designer or engineer confirms they satisfy the specification before anything is ordered. A submittal package normally contains manufacturer data sheets, test certificates, compliance statements against the specification clause, samples where required, and — for engineered items — shop drawings. The approval status returned is rarely a simple yes: "approved", "approved as noted", "revise and resubmit" and "rejected" each carry different consequences for procurement.
Why It Matters
On most building projects the submittal register, not the construction programme, is the true early-warning system. Every long-lead item — switchgear, lifts, curtain wall, chillers, specialist valves — has a manufacturing lead time that only starts counting from the day the order is released, and the order cannot be released until the submittal is approved. A four-week review cycle on a sixteen-week lead item quietly becomes a twenty-week gap. Because that gap sits in procurement rather than on site, it is invisible in a baseline schedule that only shows installation activities, which is exactly why it surprises people.
How the Loop Actually Works
- Register first. Extract every specification section requiring a submittal into a register with responsible party, target submission date, review duration and required-on-site date.
- Work backwards from installation. Required on site minus delivery lead time minus fabrication minus approval duration equals the submission deadline. That date, not the installation date, is what you drive.
- Submit complete. Partial packages are the leading cause of "revise and resubmit" — and a resubmission usually restarts the full review clock, not the remainder of it.
- Track review time contractually. Most contracts give the designer a fixed period (commonly 14 days). Log receipt dates and returns; the record matters later.
- Close the loop to procurement. Approval means nothing until the purchase order is released; someone must own that handover explicitly.
- Link to the schedule. Long-lead submittals belong in the programme as real activities with logic into the installation work.
Real-World Example
On a mid-rise hospital fit-out, the medical gas manifold submittal was returned "revise and resubmit" because a single valve model in a twelve-page package was superseded. The subcontractor corrected the page in two days, but the resubmission entered the back of the designer's queue and took another fourteen. The order released five weeks after the planned date, and the manufacturer's slot had gone: a further six-week wait. The installation activity had thirty days of float, so nobody noticed until the float was gone — and by then the commissioning window was compressed into the client's move-in period. The recovery cost, mostly premium-time commissioning, was roughly forty thousand pounds. The root cause was not the valve model; it was that nobody was tracking submittals as schedule activities.
Practical Lessons Learned
- Resubmission is the expensive event. One right-first-time package beats three quick ones — the queue, not the review, is what costs you weeks.
- "Approved as noted" is not permission to ignore the notes. Comments carry contractual weight; installing to the original submission invites a rejection at inspection.
- Designers get overloaded in waves. Submitting forty packages in one week guarantees a slow month; smooth the flow deliberately.
- Substitutions need a commercial case, not just a technical one. Equal-and-approved claims fail when the submitter cannot show performance parity clause by clause.
- The register is a live document. A submittal log updated monthly is a historical record; updated weekly it is a controls tool.
Expert Tips
- Colour the register by "days until submission deadline", not by status. Status tells you where things are; the countdown tells you what to chase.
- Hold a fifteen-minute weekly submittal stand-up with procurement, the designer's lead and the subcontractor coordinators. It removes more delay per hour than any other meeting on a fit-out.
- Pre-agree the review duration and the definition of a complete package in the subcontract, and repeat it on the cover sheet of every submission.
- For critical long-lead items, ask for a pre-submittal review — an informal look at the draft before the formal clock starts.
- Keep a one-page compliance matrix at the front of every package mapping specification clause to data-sheet page. Reviewers approve what they can verify quickly.
Common Mistakes
- Building a submittal register from the drawings rather than the specification, so half the required packages are never identified.
- Scheduling installation dates without modelling approval and fabrication as predecessor activities.
- Letting subcontractors submit directly to the designer, so the main contractor loses both visibility and the review-duration record.
- Ordering "at risk" before approval to save time, then rebuilding at your own cost when the notes come back.
- Treating samples as a formality and shipping them late, holding up an otherwise complete package.
Key Takeaways
- The submittal register is the earliest reliable predictor of procurement-driven delay.
- Drive submission deadlines backwards from required-on-site dates, not forwards from convenience.
- Right-first-time packages beat fast packages, because resubmission restarts the queue.
- Long-lead submittals belong in the programme with real logic.
- Record submission and return dates; they are the backbone of any later delay narrative.
Related Concepts
Pairs with Baseline Schedule, Change Order Management, Float Management, and Handover Pack.
Frequently Asked Questions
How long should a submittal review take?
Most contracts specify 14 calendar days, and that is a reasonable planning assumption for straightforward packages. Engineered systems with shop drawings realistically need longer, and it is better to agree 21 days up front than to plan 14 and be disappointed monthly.Does approval transfer responsibility for the product to the designer?
Almost never. Standard forms make clear that review is for general conformance with the design intent, and the contractor remains responsible for dimensions, quantities, fabrication and coordination. Approval protects you from the wrong product, not from your own errors.What is the difference between 'approved as noted' and 'revise and resubmit'?
Approved as noted lets you proceed provided you incorporate the comments; revise and resubmit does not. The practical trap is treating the first as unconditional approval. Log the comments as actions and evidence their closure, or you will meet them again at inspection.How should submittals appear in the programme?
As a short chain per long-lead package: prepare submittal, review period, order release, fabrication, delivery, then installation. Modelling only installation hides weeks of exposure and is one of the most common causes of unexplained procurement delay.Can we order before approval to protect the programme?
You can, and sometimes you should, but do it as a conscious risk decision with a written record of who accepted the exposure. Ordering at risk without that conversation is how contractors end up funding replacement materials they never priced.Who owns the submittal register?
In practice the document controller maintains it and the planner or project controls lead owns it, because the dates on it are schedule dates. When it belongs solely to document control, it becomes an administrative list rather than a forecasting tool.What is a common misconception about Material Submittal Approval?
That the topic is well-defined across all references. In practice, definitions vary between PMBOK, PRINCE2, AACE and ISO 21500 — this entry uses the definition most aligned with field practice on capital projects, and flags where the standards diverge.Which related encyclopedia entries should I read alongside Material Submittal Approval?
Read Earned Value Management, Critical Path Method and the DCMA 14-point assessment next. The full A–Z is available in the PMMilestone Encyclopedia, and quick one-line definitions live in the PM Glossary on the flagship platform.How does Dr. Hassan Eliwa's research treat Material Submittal Approval?
Dr. Hassan Eliwa's research focuses on owner-side project controls, schedule integrity and forensic delay analysis on capital construction and power programmes. Material Submittal Approval is treated through that lens — what a planning or controls engineer is expected to do with it on a live project, not its textbook definition alone. See the full research library at PMMilestone Research Articles.How is Material Submittal Approval defined on PMMilestone Research & Insights?
The formal loop through which proposed products are reviewed against the specification and approved before procurement — the quiet path that decides whether long-lead items arrive on time or six weeks late. For the full treatment, see the definition, principles, applications and related entries above — every encyclopedia entry follows the same research-grade structure.
People also ask
Follow-up questions practitioners search for next — each one points to the calculator, template or reference entry that answers it.
Which book goes deeper than this entry?
Practitioner field handbooks with worked numerical examples. Books & Publications ↗
Which calculator on PMMilestone.org applies here?
The integrated EVM workbook covers most cost-schedule diagnostics. EVM Calculator ↗
Where is this in the glossary?
Quick-lookup definitions across 1,200+ PM terms. PM Glossary on PMMilestone.org ↗
Which learning track covers this end-to-end?
Structured tracks from beginner planner to programme controls director. Project Controls Academy ↗
Related Entries
More in Construction Execution
- Letter AAs-Built Drawings Management
The disciplined capture, red-lining and issue of drawings that reflect the works as they were actually constructed, not as they were originally designed.
- Letter CCommissioning Witness Testing
The formal, client-witnessed proving of installed systems against design intent — the point where a project stops being a construction site and starts being an operating asset.
- Letter CConcrete Curing Regime
The controlled temperature, moisture and time regime applied to freshly placed concrete so that it reaches its designed strength and durability rather than the strength the weather happened to allow.
- Letter CConcrete Delivery Docket Control
The site-level discipline of checking, signing and archiving every ready-mix delivery ticket — the only reliable evidence of what was actually poured into your structure.
- Letter CConcrete Pour Card
A single-page control document that authorises a specific concrete pour by confirming design, formwork, reinforcement, embedments, weather and inspection sign-offs are all in place before the truck arrives.
- Letter DDaily Site Diary
The contemporaneous daily record of everything that happened on a construction site — labour, plant, weather, deliveries, visitors, instructions, delays — kept in chronological order and signed each day.
Further reading on PMMilestone.org
Curated companion resources hosted on the flagship platform, PMMilestone.org.
- For practitioners who want to go deeper, the Schedule Health Checker.
- Engineers researching this topic typically continue with the Failure Database.
- A practical companion to this entry is the Learning Tracks.
- Closely related on the flagship platform is the Books & Publications.
- Useful alongside this article is the PMMilestone.org knowledge hub.