Site Instruction
A written direction from the contract administrator or engineer to the contractor to carry out, vary or clarify work on site — the contractual mechanism that turns a verbal decision into an enforceable action.
Definition
A Site Instruction — often written SI, and known in some contract forms as an Engineer's Instruction or Architect's Instruction — is a formal written direction issued by the contract administrator to the contractor. It tells the contractor to do something, stop something, change something, or clarify something. It is the mechanism by which decisions made in meetings and site walks become contractually binding.
What an SI Is (and Is Not)
An SI is an instruction, not a variation. It tells the contractor to act; it may or may not have cost or time implications. A variation, or change order, is the commercial consequence of an instruction that alters the scope, cost or time. Every variation begins with an SI; not every SI becomes a variation. The distinction matters because contractors sometimes claim variation costs against SIs that were merely clarifications, and administrators sometimes issue instructions that clearly change the scope but decline to acknowledge the commercial consequences.
What Should Be on the SI
- Unique SI number, date, project name.
- Issued by (name and role) and issued to (contractor or subcontractor).
- Clear description of the instruction — what is to be done, where, and by when.
- Reference to the contract clause that gives the administrator the authority to instruct.
- Attached sketch, drawing or specification amendment where relevant.
- A note stating whether the instruction is considered to have cost and/or time implications, and if so the process by which those will be evaluated.
- Signature and distribution list.
Real-World Example
On a hotel refurbishment in Riyadh, the contract administrator held a site walk with the interior designer and the client. During the walk the client asked for the reception desk to be moved 800 mm to open the sight-line to the lift lobby. The site engineer sketched it on a print, everyone nodded, and work continued. Two months later, when the desk was already installed, the contractor submitted a variation for AED 42,000 covering the extra electrical routing and the modified stone panel. The administrator refused it — there was no SI, no written record, and no evidence that the client's verbal request had been agreed with the necessary commercial process. The dispute took six months to resolve and cost more in fees than the variation itself. The habit the contractor adopted afterwards: no work off a verbal instruction, ever. If the administrator would not issue an SI, the work did not start.
Why Written Instructions Matter
Construction contracts are unusual in the volume of decisions that get made informally in the middle of the works. Every one of those decisions has cost, time, quality and safety consequences. The SI process converts an informal conversation into a document that both parties have to stand behind. It protects the contractor from being told, six months later, that a piece of work was unauthorised. It protects the administrator from being told, six months later, that a verbal instruction is worth ten times what it seemed at the time.
SI vs RFI vs Variation
- RFI — the contractor asks a question, the administrator answers. If the answer requires new work, the answer is often issued as an SI.
- SI — the administrator instructs the contractor to act.
- Variation / Change Order — the commercial evaluation of the cost and time impact of an SI that has changed the scope.
The three form a chain. Skipping any link — usually the SI — creates the disputes that consume the project's last six months.
Practical Lessons Learned
- The contractor's rule: no SI, no work. Every crew has been told once too often to "just get on with it" and then not paid for the change.
- The administrator's rule: every SI acknowledges the commercial consequence up front, even if the answer is "no cost, no time." Silence on the commercial side is what causes the arguments.
- Verbal instructions on site do happen. The professional habit is to follow up with an email within 24 hours summarising what was agreed, and treat that email as an interim SI pending the formal one.
- Track SIs in a live register with status, associated RFI, associated variation, and closeout date. The register is the single source of truth for what has been instructed on the project.
- Never accept SIs from anyone outside the authorised signatory list. Client representatives who are not authorised to instruct create the worst disputes.
Expert Tips
- Number SIs sequentially across the project, not by discipline. A single sequence makes closeout tracking straightforward.
- Publish the authorised signatory list at kickoff and refresh it on every organisational change on either side.
- Attach the sketch or amended drawing to the SI itself, not to a follow-up email. The SI becomes self-contained and defensible.
- Distribute the SI to the same recipients as the RFI so the QS, the planner and the site team all see it simultaneously.
- Close SIs formally. An SI still marked "open" six months after the work was completed pollutes the register and makes real open items harder to see.
Common Mistakes
- Verbal instructions accepted without follow-up.
- SIs issued by people not on the authorised signatory list.
- Commercial silence — the SI is issued, the work is done, and neither party addresses the cost until much later.
- No register, so nobody knows the current SI count or status.
- Attaching amended drawings by email rather than to the SI, so the document is not self-contained.
- Confusing SIs and RFIs — the administrator answering an RFI in a way that clearly instructs new work, without recognising that an SI is now required.
Key Takeaways
- An SI is the contractual instrument that turns a decision into an enforceable action.
- No SI, no work — and no work, no dispute six months later.
- Every SI addresses the commercial consequence up front, even if the consequence is nil.
- Only authorised signatories issue SIs; the list is published and current.
- SIs live in a numbered register alongside RFIs and variations and are formally closed.
Related Concepts
Interlocks with RFI Management, Change Order Management, Change Control and Daily Site Diary. SI templates and register formats at PMMilestone.org.
Frequently Asked Questions
What is a Site Instruction?
A formal written direction from the contract administrator to the contractor to carry out, vary or clarify work — the mechanism by which verbal decisions on site become contractually binding.Is a Site Instruction the same as a variation?
No. An SI is an instruction to act; a variation is the commercial evaluation of the cost and time impact of an SI that changes the scope. Every variation is preceded by an SI, but not every SI becomes a variation.Who can issue an SI?
Only the individuals listed on the project's authorised signatory list — typically the contract administrator or their delegated representative. SIs from anyone else are not contractually binding.Can a verbal instruction stand alone?
Verbal instructions happen but should be confirmed in writing within 24 hours by the party receiving them. Contractors who act on verbal instructions without written follow-up have limited recourse if the cost is later disputed.What is the difference between an SI and an RFI?
An RFI is a question from the contractor; an SI is an instruction from the administrator. If an RFI answer requires new work, the answer is often issued as, or accompanied by, an SI.How are SIs tracked?
In a numbered register alongside RFIs and variations, showing status, associated documents and closeout date. The register is the single source of truth for what has been instructed on the project.What is a common misconception about Site Instruction?
That the topic is well-defined across all references. In practice, definitions vary between PMBOK, PRINCE2, AACE and ISO 21500 — this entry uses the definition most aligned with field practice on capital projects, and flags where the standards diverge.Which related encyclopedia entries should I read alongside Site Instruction?
Read Earned Value Management, Critical Path Method and the DCMA 14-point assessment next. The full A–Z is available in the PMMilestone Encyclopedia, and quick one-line definitions live in the PM Glossary on the flagship platform.How does Dr. Hassan Eliwa's research treat Site Instruction?
Dr. Hassan Eliwa's research focuses on owner-side project controls, schedule integrity and forensic delay analysis on capital construction and power programmes. Site Instruction is treated through that lens — what a planning or controls engineer is expected to do with it on a live project, not its textbook definition alone. See the full research library at PMMilestone Research Articles.How is Site Instruction defined on PMMilestone Research & Insights?
A written direction from the contract administrator or engineer to the contractor to carry out, vary or clarify work on site — the contractual mechanism that turns a verbal decision into an enforceable action. For the full treatment, see the definition, principles, applications and related entries above — every encyclopedia entry follows the same research-grade structure.
People also ask
Follow-up questions practitioners search for next — each one points to the calculator, template or reference entry that answers it.
Which calculator on PMMilestone.org applies here?
The integrated EVM workbook covers most cost-schedule diagnostics. EVM Calculator ↗
Where is this in the glossary?
Quick-lookup definitions across 1,200+ PM terms. PM Glossary on PMMilestone.org ↗
Which learning track covers this end-to-end?
Structured tracks from beginner planner to programme controls director. Project Controls Academy ↗
Which book goes deeper than this entry?
Practitioner field handbooks with worked numerical examples. Books & Publications ↗
Related Entries
Further reading on PMMilestone.org
Curated companion resources hosted on the flagship platform, PMMilestone.org.
- For practitioners who want to go deeper, the Project Controls Academy.
- Engineers researching this topic typically continue with the Learning Tracks.
- A practical companion to this entry is the Books & Publications.
- Closely related on the flagship platform is the EVM Calculator.
- Useful alongside this article is the Schedule Health Checker.
- Many readers follow this up with the PMMilestone.org knowledge hub.