Site Setup · Letter T

Temporary Site Power

The generators, distribution boards, transformers and cables that keep a site alive before the permanent supply exists — undersize it and the cranes stop, mismanage it and people get hurt.

By Dr. Hassan Eliwa, PhD · Founder of PMMilestone.org and PMMilestone.com · Updated 2026-08-21

Definition

Temporary site power is the complete electrical installation that serves a construction site before permanent energisation: the supply source (utility connection or generators), main distribution boards, step-down transformers to reduced low voltage (110 V in the UK, or protected 230 V with RCDs elsewhere), final circuits, leads and earthing. It is designed, installed, inspected and maintained like any electrical installation — because it is one, operating outdoors, in mud, around water, under constant mechanical abuse.

Why It Matters

Power is the invisible dependency in every programme. An undersized generator that trips when two tower cranes slew together costs a day's lifting every time it happens. A drowned cable joint in a haul route is an electrocution hazard at ankle height. And the loads change constantly — welfare cabins multiply, winter lighting arrives, dewatering starts, the tower crane arrives before the mains upgrade. Sites that treat temporary power as "the electrician's problem" discover it is actually a programme, cost and safety system that needs a load schedule, a growth plan and a named owner like any other temporary work.

How to Plan and Run It

  1. Build a load schedule — every foreseeable load with demand and diversity factors: cranes, hoists, pumps, batchers, welfare, lighting, tools, heating.
  2. Size for starting currents — direct-on-line motors draw six to seven times running current; the largest motor starting on a running system sets the generator size.
  3. Design for growth — boards with spare ways, generator sets with headroom, cable routes that accept a second run.
  4. Protect critical circuits separately — dewatering, fire pumps and safety lighting on dedicated breakers with their own backup feed.
  5. Install for the environment — armoured cable or cable ramps on haul routes, IP-rated enclosures, leads elevated or buried and marked.
  6. Inspect and test on a regime — weekly RCD tests, monthly inspections, thermographic checks on loaded boards, records kept.

Real-World Example

A city-centre frame job ran two tower cranes, two hoists and the dewatering off a single 500 kVA generator that the load schedule said was adequate — on paper, with a hopeful diversity factor. Every morning at 07:00, both hoists started together as the workforce went up, the voltage dipped, and the crane VFDs tripped on undervoltage. Twenty minutes of reset, twice a day, quietly costing a lifting hour daily. The fix was not a bigger generator; it was a ten-line staged-start procedure and moving the hoists onto a soft-start setting, agreed in one meeting with the crane supplier. The load schedule was updated with the measured starting currents, and the next project's temporary power design started from those numbers, not the brochure ones.

Practical Lessons Learned

  • kVA is not kW. At a 0.8 power factor a 500 kVA set delivers 400 kW — and motor loads pull the power factor down further. Size on real power, then add starting margin.
  • Winter doubles the load. Lighting, heating and drying arrive together in October; the schedule that worked in June fails in November.
  • Dewatering never shares. Put it on its own breaker and its own backup supply; a nuisance trip elsewhere must never stop the pumps.
  • Cable routes are logistics. Every haul route crossing needs ramps or burial before the first delivery, not after the first shredded lead.
  • The electrician needs programme visibility. Crane arrivals, pump starts and cabin moves are electrical events; put them in the look-ahead with a power impact flag.

Expert Tips

  • Clamp-meter the actual currents for a week before finalising generator size; brochure figures and real starting behaviour differ enough to matter.
  • Colour-code and label every board and transformer with circuit, source and the phone number of the responsible electrician — in an emergency, nobody reads a schematic.
  • Fit hour meters and fuel logs to generators; consumption trending catches both underloading (wet stacking) and the cabin heater someone wired in without asking.
  • Keep a single-line diagram laminated at the main board and updated at every change. It is the first thing the utility engineer, the fire service or the investigator will ask for.
  • Run generators at 60–80% load where possible; chronically light-loaded diesels glaze, smoke and fail early — arrange load banks if the site is between phases.

Common Mistakes

  • Sizing the generator on connected load × diversity wishful thinking, then discovering motor starting currents the hard way.
  • Daisy-chained splitters and domestic-grade leads feeding half the site from one 32 A socket.
  • Cables across haul routes unprotected, or buried without marking and struck by the first excavation.
  • No RCD test regime — the devices that prevent electrocution silently failed months ago.
  • Treating the temporary supply as fit-and-forget, with no named owner, no inspections and no record of the fifty modifications made since installation.

Key Takeaways

  • Temporary power is a designed installation with a load schedule, growth plan and named owner — not a commodity hire.
  • Size on measured real power and starting currents; brochure arithmetic trips cranes.
  • Critical loads — dewatering, fire, safety lighting — get dedicated circuits and independent backup.
  • Protect cables mechanically and inspect the installation on a documented regime.
  • Put electrical events — crane arrivals, pump starts, winter loads — into the programme look-ahead.

Related Concepts

Pairs with Site Mobilization Plan, Site Logistics Plan, Temporary Works Register, and Dewatering System Operation.

Frequently Asked Questions

  • How do I size a site generator properly?
    Start with a load schedule of every foreseeable demand in kW, apply honest diversity factors, then check the worst motor-starting case — the largest motor starting while everything else runs. Clamp-meter a similar site if you can; real starting currents beat brochure figures. Finally add growth margin for winter loads and late additions, which always arrive.
  • Why does the generator trip when the cranes and hoists run together?
    Usually starting currents, not running load. Direct-on-line motors draw six to seven times their running current for a second or two, and simultaneous starts stack those dips. Soft starters, staged-start procedures and VFD settings often solve it without hiring a bigger set — the measured data tells you which.
  • Isn't temporary power just the electrician's job?
    That assumption is the root of most problems. The electrician installs it, but the loads — crane arrivals, dewatering starts, welfare growth, winter heating — are programme decisions made by planners and site managers. Without a named owner and a living load schedule, the supply is always one phase behind the job.
  • What voltage should portable tools use on site?
    In the UK, 110 V centre-tapped-to-earth (the yellow system) is the standard for portable tools and site lighting because it limits shock voltage to 55 V to earth. Elsewhere, protected 230 V with 30 mA RCDs is common. Either way, the protection regime — RCD testing, inspection records — matters as much as the voltage choice.
  • How often must the temporary installation be inspected?
    A common regime is weekly RCD push-button tests, monthly documented visual inspections, and periodic formal inspection and testing — often quarterly on long projects, and after any significant modification. Thermographic surveys of loaded boards catch loose connections before they catch fire. Records of all of it are what prove diligence.
  • What backup do critical loads need?
    Dewatering pumps, fire pumps and safety lighting should sit on dedicated circuits with an independent backup feed — a second generator with auto-changeover is typical on deep excavation work. The test is simple: any single fault elsewhere on the site must not stop the critical load. If the pumps share a breaker with the welfare cabins, they will eventually share a trip.
  • Which calculators on PMMilestone.org apply to Temporary Site Power?
    For Temporary Site Power, the most relevant tools on the flagship platform are the EVM, SPI and CPI calculators on PMMilestone.org. They reproduce the formulas referenced in this entry against your own project data.
  • What is a common misconception about Temporary Site Power?
    That the topic is well-defined across all references. In practice, definitions vary between PMBOK, PRINCE2, AACE and ISO 21500 — this entry uses the definition most aligned with field practice on capital projects, and flags where the standards diverge.
  • Which related encyclopedia entries should I read alongside Temporary Site Power?
    Read Earned Value Management, Critical Path Method and the DCMA 14-point assessment next. The full A–Z is available in the PMMilestone Encyclopedia, and quick one-line definitions live in the PM Glossary on the flagship platform.
  • How does Dr. Hassan Eliwa's research treat Temporary Site Power?
    Dr. Hassan Eliwa's research focuses on owner-side project controls, schedule integrity and forensic delay analysis on capital construction and power programmes. Temporary Site Power is treated through that lens — what a planning or controls engineer is expected to do with it on a live project, not its textbook definition alone. See the full research library at PMMilestone Research Articles.
  • How is Temporary Site Power defined on PMMilestone Research & Insights?
    The generators, distribution boards, transformers and cables that keep a site alive before the permanent supply exists — undersize it and the cranes stop, mismanage it and people get hurt. For the full treatment, see the definition, principles, applications and related entries above — every encyclopedia entry follows the same research-grade structure.

People also ask

Follow-up questions practitioners search for next — each one points to the calculator, template or reference entry that answers it.

Related Entries

Browse more in this category

More in Site Setup

View all Site Setup entries →

Further reading on PMMilestone.org

Curated companion resources hosted on the flagship platform, PMMilestone.org.

Related Encyclopedia Entries
Research Articles
Career Guides
Tools on PMMilestone.org
Buy me a coffee