Concurrent Delay in Construction: How Planners Prove (or Disprove) It in the Schedule

A planner's field guide to concurrent delay — what it really means, how FIDIC, NEC4, JCT and US practice treat it, how to separate true concurrency from pacing and dominant delay, and a seven-step method for testing it in your own schedule updates.

By Dr. Hassan Eliwa, PhD — Founder of PMMilestone.org & PMMilestone.com · 2026-11-30

Reading time · 16 min · Updated 2026-11-30
Concurrent delay diagram: an employer delay and a contractor delay on two parallel critical paths both pushing the forecast completion beyond the contract completion date
Concurrent delay diagram: an employer delay and a contractor delay on two parallel critical paths both pushing the forecast completion beyond the contract completion date

The word that ends every delay meeting

I have sat in a lot of delay meetings, and most of them end the same way. The contractor presents a late design release, a late access date or a change, and shows the completion date moving. The employer's side listens politely, then someone says the word: "concurrent." The contractor's own procurement was late too. Their steel was late. Their crews were short. So, the argument goes, the employer delay did not really cause anything.

Sometimes that argument is right. More often, in my experience, it is a reflex — a word used to close the discussion rather than a finding that has been tested in the schedule. And the planner on either side who can actually test it, update by update, is the person who decides how that meeting ends.

This guide is the method I use when I am asked "is this concurrent?" — whether I am preparing an extension of time submission for a contractor, reviewing one for an owner, or helping a project team understand where it stands before a claim is ever written.

Note on examples: the project stories in this guide are drawn from real assignments, with names, figures and identifying details changed or combined to protect clients. Contract and case references are general; always read the exact wording of your own contract and take legal advice on entitlement.


What concurrent delay actually means

The most widely used definition comes from the Society of Construction Law's Delay and Disruption Protocol (2nd edition, February 2017). In plain terms, true concurrent delay is the occurrence of two or more delay events at the same time — one an employer risk event, the other a contractor risk event — whose effects are felt at the same time, and where each of them is an effective cause of delay to completion.

That last part is where most arguments fall apart. Two delays happening in the same month is not enough. The question that courts, tribunals and experts keep coming back to is whether each delay was, on its own, actually driving the completion date. If the contractor's late steel would have delayed completion by six weeks even without the employer's late design, and the employer's late design would also have delayed it by six weeks even without the steel, you may have true concurrency. If one of them was sitting on a path with float to spare, you do not.

The Protocol itself recognises that true concurrency, in this strict sense, is uncommon. What you see far more often on real projects is concurrent effect: two delay events that start at different times but whose effects overlap. AACE International's Recommended Practice 29R-03, Forensic Schedule Analysis, discusses the same territory from the US side, including the separate idea of pacing.

Four situations that all get called "concurrent"
True concurrency

Employer and contractor events start together, run together, and each independently drives completion. Rare.

Concurrent effect

Events start at different times but their critical delay overlaps. Common, and where most real disputes sit.

Pacing

One party deliberately slows non-critical work because the other party's delay already controls the finish.

Float absorption

A delay happens at the same time, but on a path with float. It overlaps on the calendar and causes no delay to completion.

Only the first two can be concurrency in the contractual sense. The last two are often mislabelled.

Why concurrency is back at the top of the agenda in 2026

Concurrency has always been the hardest part of delay analysis. Three things have made it more pressing on the projects I see this year.

⚙️ Reviewers can now find overlaps instantly. Automated schedule comparison and AI-assisted review tools will scan every update of a project and list each contractor-caused slip that overlaps an employer event. That is useful — but it also means an owner's team can produce a long "concurrency list" in an afternoon. Most of those overlaps are float absorption, not concurrency. The planner who can explain why is suddenly very valuable.

📚 The guidance is under review. The SCL Protocol was first issued in 2002 and revised in 2017, and the Society has been canvassing members on whether a third edition is needed, with critical path and quantification guidance among the topics raised. Experts are also publishing more on the difference between genuine concurrency and simply overlapping delays — FTI Consulting's April 2026 paper on competing causes is a good recent example. The direction of travel is clear: overlap alone is not going to carry an argument.

📝 Contracts are allocating concurrency expressly. More employers are adding bespoke clauses that say how concurrent delay will be treated, and English courts have been willing to enforce them. The planner can no longer assume the "default" position applies. The first job is to read the clause.


How the main contracts and jurisdictions treat it

I am a planner, not a lawyer, and you should get legal advice on your own contract. But you cannot test concurrency properly without knowing what question the contract is asking. This is the summary I keep on my desk.

Contract / jurisdiction What it says about concurrency What it means for the planner
📘 FIDIC 2017 (Red, Yellow, Silver) Sub-Clause 8.5 deals with concurrency for the first time, but sends the assessment to the rules and procedures in the Particular Conditions. There is no definition in the General Conditions. Check the Particular Conditions first. If they are silent, the governing law fills the gap.
📗 NEC4 ECC No express concurrency clause. Compensation events are assessed prospectively against the Accepted Programme (clause 63). The quality of the Accepted Programme and the timing of the assessment matter more than a retrospective concurrency debate.
📙 JCT and English law The "Malmaison" approach (Henry Boot v Malmaison, 1999): the contractor gets the extension for the employer delay; it does not recover loss and expense for the concurrent period. Parties can contract out — North Midland Building v Cyden Homes (Court of Appeal, 2018) upheld a clause that excluded concurrent delay from the extension. Time but no money, unless the contract says otherwise. Read the extension clause for any concurrency wording.
🏴 Scotland City Inn v Shepherd (Inner House, 2010) allowed apportionment between competing causes. You may need to show the relative causative weight of each delay, not just whether both existed.
🇺🇸 United States (general practice) Where delays are truly concurrent and cannot be separated, the usual outcome is a time extension with no delay damages to either side. Pacing is a recognised concept. Expect to be asked to apportion; contemporaneous evidence of pacing is essential.
🧭 SCL Protocol (2nd ed., 2017) Guidance, not law. Core Principle 10: where concurrency is established, the contractor's delay should not reduce the extension due for the employer delay. Recovery of cost for the concurrent period is generally not available unless separable. Persuasive in many markets, but the contract always overrides it.

The planner's three tests

Whatever the contract, every concurrency argument I have seen succeed or fail has turned on three questions. I ask them about each pair of delay events before I do anything more sophisticated.

  1. Was each delay on the critical path at the time? Not the as-built critical path drawn at the end, but the path that was driving completion in the update current when the delay occurred.
  2. Would each delay, on its own, have delayed completion? Remove one event in a copy of the update and reschedule. If the finish does not move, the other event was not an independent cause.
  3. Did their effects actually overlap in time? Measure the overlap in working days, using the dates when each delay began to consume critical time, not the dates when someone first wrote a letter about it.

If the answer to all three is yes, you are probably looking at real concurrency and the contract's rule applies. If any answer is no, you have something else — and it usually helps one side considerably.


A seven-step method to test concurrency in your schedule

This is the routine I follow. It works in P6, MS Project or Asta, and it fits inside a contemporaneous windows analysis or a time impact analysis. Our delay analysis field guide covers the methods themselves in more depth.

Concurrency testing at a glance
  1. Step 1Read the clause
  2. Step 2Validate the updates
  3. Step 3Define windows
  4. Step 4Trace the driving path
  5. Step 5Attribute every slip
  6. Step 6Run the "but-for" test
  7. Step 7Document & narrate

Step 1 — Read the concurrency and EOT clauses first

Find the extension of time clause, any concurrency wording, the notice requirements and the definition of the programme the contract treats as the measuring stick. Note whether assessment is prospective (as NEC4 broadly expects) or allows retrospective analysis. This tells you which updates matter and what "proof" will look like.

Step 2 — Validate the contemporaneous updates

Concurrency analysis is only as good as the updates underneath it. Before using any update, check that the data date is correct, actual dates are recorded, there are no open ends or unexplained hard constraints, and the out-of-sequence settings have not changed between updates. I have seen an entire concurrency argument collapse because one month's update was run with Progress Override and the next with Retained Logic — the "contractor delay" was a setting change. Our guide to out-of-sequence progress in P6 explains how much that one option can move a critical path.

Step 3 — Define analysis windows around the events

Break the period into windows, usually bounded by consecutive updates. Where an important event falls mid-month, split the window at that date. Each window must have a "before" and "after" schedule you can stand behind.

Step 4 — Trace the driving path in each window

For each window, identify the longest path to completion at the start and at the end. In P6, I use the longest-path filter and then trace driving relationships backwards from the completion milestone, and I record near-critical paths within five to ten working days. Concurrency almost always lives in the gap between the critical path and the second path, so you need both.

Step 5 — Attribute every day of critical slip

Measure how much the forecast completion moved in the window, then attribute each day of movement to a cause on the driving path: employer risk, contractor risk, neutral (such as exceptional weather, depending on the contract), or unexplained. Unexplained days are a warning sign about the updates, not a category to hide.

Step 6 — Run the "but-for" test on each competing event

Where an employer event and a contractor event both appear on driving or near-driving paths in the same window, make two copies of the window's opening schedule. In copy A, insert only the employer event as a fragnet. In copy B, insert only the contractor event. Reschedule both. If each copy alone moves completion by a similar amount over the same period, you have evidence of concurrency. If only one moves it, the other was absorbing float.

"But-for" test in one window — illustrative
  1. Actual update (both events)+22 wd
  2. Copy A · employer event only+20 wd
  3. Copy B · contractor event only+6 wd
Here the contractor event overlaps on the calendar but would only have delayed completion by 6 working days. Concurrency, if any, is limited to that overlap — not the full 22.

Step 7 — Document and narrate every finding

For each window, record the driving path before and after, the slip, the attribution, the but-for results and the evidence (letters, RFIs, site diaries, delivery records). Then write it up in plain language. The same disciplines from our guide to writing a schedule narrative reviewers trust apply: numbers, dates and references, not adjectives.


Real-world example: the hospital chillers that were not concurrent

On a regional hospital extension, the employer's design team released the revised mechanical layouts for the plant room about seven weeks late. The contractor submitted an extension of time. The employer's response was immediate: the contractor's chillers had also arrived late, so the delay was concurrent and no extension was due.

On a calendar, it looked convincing. Both delays sat in the same ten-week period. But when we traced the driving path in the updates current at the time, the plant room installation could not start until the revised layouts were issued, and the chillers were not needed until the plant room pipework was substantially complete. In the but-for test, the late chillers alone would have delayed completion by four working days. The late design alone moved it by 33.

The contractor's delay was real, and the contractor did not pretend otherwise. But it was absorbing float created by the employer's delay. The extension was eventually agreed at 31 working days, with the contractor accepting that a short overlap at the end had genuinely competing causes.

💡 Lesson learned: "Both late at the same time" is a calendar statement. Concurrency is a critical-path statement. Always ask which delay the successor was actually waiting for.

Real-world example: the pacing claim with no paper trail

On a highway interchange, the owner's utility diversions ran several months late, holding up the main bridge deck. During the same period the contractor's earthworks progress fell well behind plan. When the owner raised concurrency, the contractor responded that it had deliberately paced the earthworks — there was no point pushing them while the bridge was stuck.

That may well have been true. The problem was that nothing at the time said so. Monthly reports blamed the earthworks shortfall on plant breakdowns and wet weather. No letter recorded a decision to slow down. The look-ahead schedules still showed the original earthworks rates. When the matter reached an adjudicator, the pacing argument was given very little weight and part of the period was treated as concurrent.

💡 Lesson learned: Pacing has to be a decision you can show, not a story you tell later. If you choose to slow non-critical work because of the other party's delay, write it down at the time: what you are slowing, why, and that you can resume full rate when the constraint lifts.

Real-world example: the clause that changed the question

On a residential tower under an amended JCT form, the employer had added a sentence to the extension clause stating that any delay caused by a Relevant Event which was concurrent with a delay for which the contractor was responsible would not be taken into account. It is very similar in effect to the wording upheld in North Midland v Cyden Homes.

The contractor's first submission argued the Malmaison "time but no money" position. It was a well-written argument and completely beside the point. Under that clause, the only route to an extension was to show the contractor's own delay was not concurrent — that it was absorbing float or occurring on a non-driving path. We rebuilt the analysis around that question, and around 60% of the time originally claimed was eventually recovered.

💡 Lesson learned: The contract decides which question your analysis has to answer. Read the amendments before you choose your method.


Pacing delay: the concurrency defence most people get wrong

Pacing is a party's deliberate decision to slow its own work because the other party's delay already controls the completion date. Used properly, it is a legitimate answer to a concurrency allegation: there is no point spending money to finish a section early when it will only sit waiting.

In my experience, a pacing argument holds up when four things can be shown:

  • 🧭 The other party's delay was already on the critical path when the pacing began, and was expected to stay there.
  • 📝 The decision was contemporaneous. A letter, meeting minutes or a revised look-ahead recorded the choice to slow down at the time.
  • 💪 You could have gone faster. Resources, materials and access were available for the original rate.
  • 🔁 You resumed when the constraint lifted and the paced work did not itself become critical.

Without those, "we were pacing" usually sounds like a reason invented after the fact — because, too often, it is.


Using AI tools for concurrency analysis

I now use AI-assisted comparison and review tools on almost every delay assignment. They are excellent at the mechanical work. They are not yet good at the judgement.

✅ Let the tools do this 🧠 Keep this for yourself
Compare every update and list changed logic, durations and constraints Decide whether a change was legitimate progress or schedule manipulation
Flag every overlap between employer and contractor slips Decide which overlaps were on the driving path
Extract dates from correspondence and site diaries Judge what a letter actually meant and when the delay truly started
Draft first-pass window summaries Write and sign the final narrative and opinion

A tool that lists 140 "concurrent" overlaps has done you a favour. It has given you the list to disprove.


Common mistakes (and what to do instead)

❌ Common mistake ✅ What to do instead
Treating any overlap on the calendar as concurrency Test whether each event was on the driving path and an independent cause
Using the as-built critical path to judge events that happened months earlier Use the update that was current when each event occurred
Assuming the Malmaison or SCL position applies Read the EOT clause and any amendments first
Claiming pacing with no contemporaneous record Record pacing decisions in letters, minutes and look-aheads at the time
Ignoring near-critical paths Track the second and third paths in every window
Running updates with inconsistent scheduling options Check settings in every update before analysis; log any differences
Contractors denying any delay of their own Acknowledge genuine contractor delay and show why it was not driving — credibility wins more days
Owners listing overlaps without analysis Run the but-for test before alleging concurrency in correspondence

My concurrency checklist

Before I sign off any opinion on concurrent delay, it has to pass this list.

  • The concurrency rule under this contract is written down in one sentence
  • Every update used has been validated and its scheduling options recorded
  • Windows are defined, with before and after schedules for each
  • Driving and near-critical paths are identified in each window
  • Every day of completion movement is attributed to a cause
  • Competing events have been through the but-for test
  • Any pacing claim is supported by contemporaneous documents
  • Overlap is measured in working days, from when each delay became critical
  • Evidence is referenced for every event (letters, RFIs, diaries, deliveries)
  • The narrative states clearly what is concurrent, what is not, and why

Practical lessons from the planner's desk

  • Build the defence in the baseline. A baseline with clean logic and honest durations makes concurrency far easier to test later. Our guide to getting a baseline approved first time is where this starts.
  • Know whose float is being used. Many concurrency disputes are really float disputes in disguise. The float ownership guide explains why the answer depends on the contract.
  • Notify early, analyse properly. A prompt notice with a short but-for analysis is worth more than a perfect report two years later. See our guide to preparing an EOT claim that gets awarded.
  • Keep your own delays honest. Contractors who admit their real delays and show why they were not driving are believed. Those who claim to be perfect rarely are.
  • Recovery is not an admission. Mitigating your own delay while an employer delay is running can be good practice. Record the cause and reserve your position. Our recovery schedule guide covers how.
  • Learn the vocabulary. Terms like time impact analysis, float management and critical path method are used precisely in delay disputes. Make sure you use them the same way the other side's expert does.

❓ Frequently asked questions

  • What is concurrent delay in construction?
    Concurrent delay is a situation where an employer-caused delay and a contractor-caused delay happen at the same time, or have effects that overlap, and each is an effective cause of delay to the completion date. Overlap on the calendar is not enough: each delay must have independently driven completion.
  • What is the difference between true concurrency and concurrent effect?
    True concurrency means two delay events start and run at the same time and each independently delays completion. Concurrent effect describes events that start at different times but whose critical effects overlap. The SCL Protocol treats true concurrency as uncommon; concurrent effect is far more common on real projects.
  • Does the contractor get an extension of time for concurrent delay?
    It depends on the contract and the governing law. In England the usual default, following Henry Boot v Malmaison, is that the contractor gets the extension but no loss and expense for the concurrent period. Contracts can change this — North Midland v Cyden Homes (2018) upheld a clause excluding concurrent delay from the extension. Always check your own contract.
  • How does FIDIC 2017 deal with concurrent delay?
    FIDIC 2017 Sub-Clause 8.5 addresses concurrency, but it does not define it or set a rule in the General Conditions. It refers the assessment to the rules and procedures in the Particular Conditions. If the Particular Conditions are silent, the governing law and general practice fill the gap.
  • What is pacing delay?
    Pacing delay is a deliberate slowing of non-critical work by one party because the other party's delay already controls the completion date. To be credible, a pacing decision should be recorded at the time, the party must have been able to work faster, and the paced work must not itself have become critical.
  • How do I prove concurrent delay in Primavera P6?
    Use validated contemporaneous updates, define analysis windows, trace the longest and near-critical paths in each window, attribute each day of completion slip to a cause, and run a but-for test by inserting each competing event alone in a copy of the window's opening schedule. If each event alone moves completion over the same period, that supports concurrency.
  • Can the employer claim liquidated damages during concurrent delay?
    Under the common English approach, if the contractor is entitled to an extension for the employer delay, liquidated damages cannot be levied for that period, even though the contractor's own delay was concurrent. A bespoke clause can change this, so the contract wording is decisive.
  • Can AI tools identify concurrent delay?
    AI and schedule comparison tools can quickly list every overlap between employer and contractor slips across all updates. They cannot yet reliably decide which delays were on the driving path or independent causes of delay. Use them to build the list, then test each item with critical path analysis and evidence.

Written by Dr. Hassan Khames Eliwa, PhD — planning and project controls practitioner and founder of PMMilestone. The views and examples in this guide are based on professional experience and are provided for education; they are not legal advice. Concurrency is decided by the wording of your contract and the law that governs it, so always read your own contract and take commercial or legal advice where entitlement is in question.

People also ask

Follow-up questions practitioners search for next — each one points to the calculator, template or reference entry that answers it.

  • Which books deepen this career path?

    Field handbooks on project controls, P6 scheduling and EVM. Books & Publications ↗

  • Which academy track maps to this career step?

    Structured progression from planner to programme controls director. Project Controls Academy ↗

  • Which calculator should I learn first?

    PV / EV / AC / CV / SV / CPI / SPI in one workbook — the gateway tool. EVM Calculator ↗